Projects

What we build, at what scale, in what time

Since 2009 our team and partner factories have delivered more than 3,000 production-line projects and 16,000 machines to customers in 58 countries. Below, for each industry: cases told end to end, from the starting point to acceptance tests and results, and the projects we deliver most often, with their usual equipment, output and schedule. Ask us for references in your country and industry.

Production-line projects
3,000+
Machines delivered
16,000+
Cases told end to end
5
Project types described
11

Battery and energy storage

The battery and energy storage solution
  • Representative case PowerMake

    8 PPM module and PACK line for a storage integrator in the Gulf

    An integrator that imported finished PACKs moved assembly into its own hall: one 55 m line built for a 60 Hz grid, first PACK about six months after contract.

    Output
    ≈ 2.4 GWh a year, two shifts
    Takt at site acceptance
    8.0 PPM over 72 h
    First-pass yield
    99.3 % (equipment)
    Contract to first PACK
    ≈ 6 months
    • Cell test and sorting
    • Busbar laser welding
    • PACK assembly and EOL
    • MES link
    • Pulsed laser cleaner
    • Installation and training
  • Typical scope PowerMake

    8 PPM energy-storage module and PACK line

    A fully specified prismatic line for a storage integrator moving PACK assembly into its own market.

    Output
    ≈ 2.46 GWh a year (314 Ah)
    Stations
    21 in three segments
    Footprint
    55 × 9 × 3.5 m
    Schedule
    ≈ 5–7 months to production
    • Cell test and sorting
    • Stacking and busbar laser welding
    • PACK assembly
    • EOL and air-tightness test
    • MES
    • Installation and ramp-up

    Typical markets · Gulf states, India, Southeast Asia

  • Typical scope Power

    Semi-automatic PACK line for C&I storage

    A smaller line with manual and semi-automatic stations, for commercial and industrial storage cabinets at lower volume.

    Output
    ≈ 0.2–0.5 GWh a year
    Stations
    ≈ 10–14
    Staff
    ≈ 12–20 per shift
    Schedule
    ≈ 3–5 months to production
    • Cell sorting
    • Manual stacking with fixtures
    • Laser welding station
    • PACK assembly
    • EOL test
    • Operator training

    Typical markets · Africa, Latin America, Central Asia

  • Representative case Make

    From plasma and TIG to fiber laser: a sheet-metal job shop in Central Europe

    A 35-person shop stopped outsourcing stainless cutting and welds thin stainless about four times faster, with a smaller laser than it first asked for.

    Cutting
    2.2 kW fiber, 1500 × 3000 mm
    Welding
    2 × 1.5 kW handheld
    Weld finishing
    200 W pulsed cleaner
    Order to production
    12 weeks
    • Sample tests on six parts
    • Cutter, welders, cleaner
    • Fume extraction
    • EU documents
    • Installation and training
  • Typical scope Make

    Sheet-metal workshop: cut, bend, weld, finish

    A job shop moving from plasma and TIG to fiber laser cutting and handheld laser welding.

    Cutting
    6 kW fiber laser, exchange table
    Forming
    2 CNC press brakes
    Welding
    2 handheld laser welders
    Schedule
    ≈ 8–12 weeks to production
    • Sample tests on customer parts
    • Shop layout and utilities
    • Laser cleaning for weld prep
    • Fume extraction
    • Installation and training

    Typical markets · Middle East, Eastern Europe, Latin America

  • Typical scope Make

    Laser cleaning for maintenance and restoration

    Pulsed and continuous laser cleaners replacing sandblasting and chemicals for a maintenance team.

    Machines
    1 pulsed + 2 continuous-wave cleaners
    Uses
    Moulds, rust, paint, weld prep
    Consumables
    No abrasive or chemicals
    Schedule
    ≈ 3–5 weeks to site
    • Surface tests in Wuhan
    • Laser-safety kit and training
    • Spare lenses and nozzles
    • Video support

    Typical markets · Oil and gas, shipyards, power plants

Automotive and EV parts

The automotive and ev parts solution
  • Representative case Make

    Pulsed laser cleaning for tyre moulds in South Asia

    A tyre plant moved mould cleaning from off-line dry-ice blasting to laser cleaning in the press, and cut press downtime per mould from about 4.5 hours to 1.5.

    Machines
    2 × 200 W pulsed
    Where
    In the press, while hot
    Downtime per mould
    ≈ 1.5 h instead of ≈ 4.5 h
    Order to site
    4 weeks
    • Tests on mould segments
    • Pulsed laser cleaners
    • Laser-safety plan
    • Training on three shifts
    • Wear parts
  • Typical scope MakeSense

    Hairpin stator laser welding cell

    A fiber-laser welding cell with vision positioning for an EV motor supplier starting local production.

    Process
    Fiber laser, vision-guided
    Inspection
    Post-weld vision check
    Traceability
    Per-stator records
    Schedule
    ≈ 4–6 months to production
    • Weld trials on customer stators
    • Cell with fixtures and guarding
    • MES connection
    • Run-off in Wuhan
    • Installation and training

    Typical markets · Mexico, Turkey, Thailand, India

  • Typical scope Make

    Assembly and test line for automotive parts

    A semi-automatic line with pressing, screw-driving, laser marking, leak and end-of-line test for a tier-2 supplier.

    Stations
    ≈ 8–16
    Traceability
    Laser-marked codes, MES
    Tests
    Leak and functional EOL
    Schedule
    ≈ 4–7 months to production
    • Process and cycle-time study
    • Error-proofing
    • Gauges for capability studies
    • Run-off with customer parts
    • Launch support

    Typical markets · Mexico, Morocco, Eastern Europe

  • Representative case Connect

    Pre-terminated cabling and optics for a 200-rack data hall in Southeast Asia

    A colocation operator opened its second data hall on the planned date, with cabling made to its rack drawings, labelled for the installer and tested piece by piece.

    Racks
    200
    Assemblies
    ≈ 7,800 trunks, cassettes, cords
    Transceivers
    ≈ 1,400, 25G–400G
    Order to delivery
    5–6 weeks
    • Polarity and length check
    • MPO trunks and cassettes
    • Patch cords
    • Coded transceivers
    • Packing by row
  • Typical scope Connect

    Data-hall cabling for a colocation build

    Pre-terminated structured cabling and optics for a new data hall, labelled by row and rack for the installer.

    Scale
    ≈ 200 racks
    Backbone
    MPO-12/24 trunks, OS2 and OM4
    Optics
    100G–400G transceivers
    Testing
    Insertion loss per assembly
    • Design check and polarity plan
    • Trunks, cassettes and panels
    • Patch cords
    • Transceivers coded for the switches
    • Packing by row

    Typical markets · Gulf states, Southeast Asia, Eastern Europe

  • Typical scope ConnectPowerSense

    Edge data center: cabling plus battery backup

    Fiber cabling, optics, battery storage for backup and temperature sensing for a regional edge site, under one contract.

    Scope
    Connect + Power + Sense
    Backup
    Lithium battery storage
    Monitoring
    Fiber temperature sensing
    Contract
    One, for all three
    • Structured cabling
    • Transceivers
    • Battery storage cabinets
    • Temperature monitoring
    • Commissioning support

    Typical markets · Africa, Central Asia, Southeast Asia

Telecom and FTTx networks

The telecom and fttx networks solution
  • Representative case Connect

    FTTH materials for 30,000 homes in East Africa, in four lots

    An ISP moving from fixed wireless to fiber bought every passive item for two cities from one supplier, lot by lot to its rollout plan, at prices fixed for three lots.

    Homes passed
    ≈ 30,000, phase 1
    Split
    1:64, two stages of 1×8
    Cable
    ≈ 410 km duct and ADSS
    Delivery
    4 lots over 9 months
    • BOM check
    • Cable and closures
    • PLC splitters and terminals
    • Pre-connectorised drops
    • Per-reel test reports
  • Typical scope Connect

    FTTH rollout materials for an ISP

    Everything from the central office to the home for a city-wide FTTH build, delivered in lots to the rollout plan.

    Scale
    Tens of thousands of homes passed
    Fiber
    G.652.D feeder, G.657.A2 drops
    Split
    PLC 1×8 and 1×16
    Delivery
    Staged lots over the rollout
    • Duct and aerial cable
    • Splitters, closures and boxes
    • Pre-connectorised drops
    • Splicers and OTDRs
    • Per-reel test reports

    Typical markets · Africa, Middle East, Latin America

Fiber-optic cable plants

The fiber-optic cable plants solution
  • Typical scope Connect

    Optical cable plant for a national market

    A first plant making the drop, duct and ADSS cable a country imports today, with fiber supplied from Optics Valley.

    Products
    Drop, duct and ADSS cable
    Lines
    Coloring, loose tube, stranding, sheathing
    Lab
    Optical, mechanical and climate tests
    Schedule
    ≈ 9–14 months to first cable
    • Market and product-mix study
    • Plant layout and utilities
    • Lines and test lab
    • Training in Wuhan
    • Long-term fiber supply

    Typical markets · Africa, Middle East, Central Asia

  • Typical scope Connect

    Patch-cord and pigtail assembly plant

    A compact plant assembling and testing patch cords, pigtails and pre-connectorised drops for local operators.

    Products
    Patch cords, pigtails, drops
    Equipment
    Polishing, end-face and IL/RL test
    Space
    Fits an existing light-industrial unit
    Schedule
    ≈ 3–5 months to production
    • Workstation layout
    • Polishing and test equipment
    • Connectors and cable supply
    • Operator training
    • Quality procedures

    Typical markets · Africa, Latin America, South Asia

“Typical scope” describes a kind of project. A “Representative case” tells a project of that kind end to end, with the scope, tests and figures such projects usually have, but no customer, country or year. Projects shown as “Delivered” name the country and year; customer names stay private unless the customer agrees.

Start a project

Ask for references in your country

An empty plant, a part, a network or a product idea. Tell us where you are starting. An engineer replies with a plan and a quote.