Representative case PowerMake

8 PPM module and PACK line for a storage integrator in the Gulf

An integrator that imported finished PACKs moved assembly into its own hall: one 55 m line built for a 60 Hz grid, first PACK about six months after contract.

Output
≈ 2.4 GWh a year, two shifts
Takt at site acceptance
8.0 PPM over 72 h
First-pass yield
99.3 % (equipment)
Contract to first PACK
≈ 6 months

The starting point

Where they started

Customer
A battery energy-storage integrator that builds commercial and utility cabinets and, until this project, imported finished PACKs from China.
Where
Gulf region
Before
An empty 70 × 24 m hall, 314 Ah LFP prismatic cells from a Chinese cell maker under contract, a plan to move to 500 Ah-plus cells within two years, and a local-content target in its own supply contracts.

Requirements

What they needed

  • About 2.4 GWh a year on two shifts, with modules of 13 cells and PACKs in the customer’s own housing
  • Every machine built for the site’s 400 V, 60 Hz supply, not China’s 380 V, 50 Hz
  • Stations that can be re-tooled for 500 Ah-plus cells instead of replaced
  • Equipment-caused first-pass yield of at least 99 %, written into the contract
  • Local operators and maintenance staff able to run the line without expatriates after ramp-up

What we supplied

Equipment, by stage

  • Power

    Cell processing

    • Robotic depalletizing with vision
    • Barcode scan, OCV test and NG reject
    • Cell flipping and grouping
    • Manual adhesive station
    The 8 PPM line on Stratavolt
  • Power

    Module stacking and welding

    • Two stacking and pressing stations
    • Terminal addressing and polarity check
    • Busbar laser welding
    • Module EOL test
  • Power

    PACK assembly and test

    • Cooling-plate leak test
    • Automatic thermal-adhesive dispensing
    • Six PACK assembly stations
    • PACK EOL and full-pack leak test
  • Make

    Around the line

    • 200 W pulsed laser cleaner (Maxwave MW-C200) for fixture and terminal rework
    • MES link for per-cell traceability
    • Spare-parts kit worth about 2 % of the equipment
    • Laser-safety guarding and training
    Pulsed laser cleaners on Maxwave

Acceptance

How it was proven

  1. Factory acceptance in Wuhan with 2,000 of the customer’s own cells: four hours at rated takt, pull tests and cross-sections from every welding head, and the full set of EOL records
  2. Two of the customer’s engineers in Wuhan for the FAT; the rest of the team watched live on video and received the recording and the data
  3. Site acceptance: 72 hours at rated takt with production cells, first-pass yield counted on equipment causes only, as the contract defined it

Results

What it achieved

Takt at factory acceptance
8.2 PPM over 4 hours
Takt at site acceptance
8.0 PPM over 72 hours
First-pass yield, equipment causes
99.3 %
Operators per shift
21, as designed
Contract to first PACK
≈ 6 months
Trained on site
28 operators, 4 maintenance technicians

Schedule

From contract to running

  1. 01

    Scope and cell trials

    Scope aligned station by station; the customer’s cells run through stacking, welding and EOL trials in Wuhan.

    Weeks 1–4

  2. 02

    Build and FAT

    Line built for 400 V, 60 Hz; factory acceptance with 2,000 customer cells, on video.

    Weeks 5–16

  3. 03

    Ship

    Crated by segment; sea freight and customs clearance with the conformity certificates the destination requires.

    Weeks 17–21

  4. 04

    Install and commission

    Four ZeroLine and Stratavolt engineers on site; first PACK off the line at the end of commissioning.

    Weeks 22–25

  5. 05

    Site acceptance and ramp-up

    72-hour run, then shift-by-shift ramp-up to rated takt by week 33.

    Weeks 26–33

Who did what

One contract, several factories

ZeroLine

  • Put three competing quotes side by side station by station, so the customer compared like with like
  • One contract for the line, the laser cleaner, the MES link and the spare parts
  • Set the FAT protocol with the customer, witnessed it and sent the video and data
  • Export documents, conformity certificates, freight and insurance
  • Led installation and training on site; remote support in the customer’s working hours

The factories

  • Stratavolt designed, built and commissioned the line and ran the factory acceptance test
  • Maxwave Laser built and tested the pulsed laser cleaner
How the work is split on every project

Write down how yield is counted before you sign. “Equipment-caused” and “all causes” can differ by several points in the first weeks, while operators are still learning.

What we tell the next buyer