Delivered · Bangladesh
300 MW photovoltaic module production line delivered in Bangladesh
Turnkey 300 MW crystalline-silicon solar PV module production line delivered from factory acceptance in China to cleanroom installation, commissioning and production ramp-up in Bangladesh.
- Annual capacity
- 300 MW / year
- Laser cell cutting
- ≤ 0.05 % breakage (Grade A)
- Stringer positioning
- ±0.05 mm CCD vision
- Delivery scope
- FAT · Export · On-site SAT
On-site acceptance & commissioning
Turnkey handover & cleanroom commissioning bay
-
Process engineer inspecting soldered multi-busbar cell string at CTM-BC60 -
300 MW PV module production line turnkey acceptance in Bangladesh -
CTC-72S-BC dual-lane non-destructive laser cell cutter during cleanroom run -
Dual-lane soldered half-cell strings on stringer outfeed conveyor
The starting point
Where they started
- Customer
- A solar module manufacturer in Bangladesh establishing local automated crystalline-silicon photovoltaic module production for domestic utility, commercial and industrial rooftop projects.
- Where
- Bangladesh
- Before
- A prepared cleanroom factory hall in Bangladesh transitioning from imported finished solar panels to local automated cell cutting, multi-busbar stringing, layup, lamination, framing and end-of-line IV/EL testing.
Requirements
What they needed
- 300 MW annual PV module output across single-glass and dual-glass module formats (1,640–2,600 × 950–1,500 mm)
- Water-assisted non-destructive laser cell cutting keeping Grade A cell breakage at or below 0.05 % with ±0.05 mm CCD positioning
- High-speed infrared multi-busbar stringing compatible with 166–210 mm half-cut cells and low-temperature solder control
- Witnessed factory acceptance testing (FAT) on reference cells before reinforced fumigation-free export crating
- On-site cleanroom installation, joint Chinese-Bangladeshi commissioning, operator training and production ramp-up
What we supplied
Equipment, by stage
-
Power
Non-destructive cell cutting & stringing
- Water-assisted non-destructive laser cell cutters (CTC-72S-BC / CTC-80S-BC class, ≤ 500 mm/s scribing) with pulsed grooving, CW thermal splitting and CCD vision alignment (≤ 0.05 % breakage)
- High-speed automated multi-busbar infrared stringers (CTM-BC60 / CTM-72 class) with PLC recipe changeover, ±0.05 mm repeat positioning, ±7.5 °C closed-loop thermal control and ≥ 0.5 N solder peel force
- Inline cell defect screening and string electroluminescence (EL) inspection before layup
-
Power
Layup, bussing & encapsulation
- Automated string layup and bussing stations (≤ 45 s cycle in half-cell mode, up to 99 % equipment uptime)
- EVA/POE film, glass loading and pre-lamination visual & EL inspection stations
- Multi-chamber vacuum laminators configured for single-glass and bifacial dual-glass modules
-
Power
Framing, curing & EOL testing
- Automated edge trimming, framing, junction-box potting and silicone curing line
- AAA-class solar simulator IV flash testing, hi-pot safety testing and final EL inspection
- Automated module sorting, grading and palletizing stations
-
Power
Turnkey engineering & site handover
- Cleanroom layout, 230/400 V 50 Hz power distribution, compressed-air (0.6–0.8 MPa) and chilled/DI water utility engineering
- Station-by-station fumigation-free wooden export crating and sea freight to Bangladesh
- Joint on-site installation, calibration, operator/maintenance training and formal turnkey acceptance
Acceptance
How it was proven
- Pre-shipment factory acceptance test (FAT) in China running reference 182/210 mm multi-busbar cells through laser cutting and high-speed stringing against contractual breakage and positioning limits
- Pre-dispatch QC verification of every wooden export crate, utility manifold and spare-parts kit prior to container loading
- On-site installation, cleanroom commissioning run, operator certification across shifts and formal joint turnkey handover in Bangladesh
Results
What it achieved
- Delivered line capacity
- 300 MW / year
- Destination
- Bangladesh
- Cell breakage (laser cutting)
- ≤ 0.05 % (Grade A)
- Vision repeat accuracy
- ±0.05 mm
- Half-cell layup & bussing
- ≤ 45 s per module
- Acceptance status
- Turnkey SAT signed off
Schedule
From contract to running
- 01
Cell spec & cleanroom layout
Reference cell drawings, module dimensions, cleanroom floor plan and utility loads finalized.
Phase 1
- 02
Equipment build & FAT
Laser cutters, stringers and module-line stations built and accepted on reference cells in China.
Phase 2
- 03
Export crating & sea shipment
Reinforced wooden crates numbered by line station and shipped to Bangladesh with customs documentation.
Phase 3
- 04
On-site install & calibration
Commissioning engineers dispatched to Bangladesh for mechanical alignment, utility hookup and recipe tuning.
Phase 4
- 05
Joint acceptance & ramp-up
Local engineering and operator shifts trained through live module production and turnkey handover.
Completed
Who did what
One contract, several factories
ZeroLine
- Coordinated line layout, utility specifications and station-to-station takt balancing under one turnkey scope
- Aligned reference-cell tooling, ribbon specs and FAT acceptance criteria before production build
- Managed reinforced export crating, shipping documentation and spare-parts provisioning
- Dispatched experienced PV commissioning engineers to Bangladesh for installation, training and production ramp-up
The factories
- Strategic PV equipment factory engineered and built the non-destructive laser cutters, high-speed stringers and module packaging line
- Executed pre-shipment factory acceptance runs and supplied on-site process & automation engineers for handover
Lock the reference solar cell drawing, busbar count and module frame range into the technical agreement before build — every change of cell format requires matched ribbon guides and vision recipes.
Behind this project
The solution and services it used
- Solar, storage and EV charging Commercial sites, mines, towers and microgrids that cut diesel and peak tariffs.
- Sourcing and factory audit The right factory for your job, audited on site and compared like for like.
- Factory acceptance and inspection Nothing ships before it has run. You watch the test, then you pay.
- Shipping and compliance Export documents, crating, one consolidated shipment, and the papers your market needs.
- Installation and training Engineers on your site until it runs at rate, and a team that can run it after.
More cases
Other projects, end to end
- 8 PPM module and PACK line for a storage integrator in the Gulf An integrator that imported finished PACKs moved assembly into its own hall: one 55 m line built for a 60 Hz grid, first PACK about six months after contract.
- From plasma and TIG to fiber laser: a sheet-metal job shop in Central Europe A 35-person shop stopped outsourcing stainless cutting and welds thin stainless about four times faster, with a smaller laser than it first asked for.
- FTTH materials for 30,000 homes in East Africa, in four lots An ISP moving from fixed wireless to fiber bought every passive item for two cities from one supplier, lot by lot to its rollout plan, at prices fixed for three lots.
- Pre-terminated cabling and optics for a 200-rack data hall in Southeast Asia A colocation operator opened its second data hall on the planned date, with cabling made to its rack drawings, labelled for the installer and tested piece by piece.
Factory quote