Representative case Connect

Pre-terminated cabling and optics for a 200-rack data hall in Southeast Asia

A colocation operator opened its second data hall on the planned date, with cabling made to its rack drawings, labelled for the installer and tested piece by piece.

Racks
200
Assemblies
≈ 7,800 trunks, cassettes, cords
Transceivers
≈ 1,400, 25G–400G
Order to delivery
5–6 weeks

The starting point

Where they started

Customer
A colocation operator building its second data hall, with a local contractor installing the cabling.
Where
Southeast Asia
Before
Rack elevation drawings, a spine-and-leaf design with 400G uplinks, and a hall-ready date nine weeks away.

Requirements

What they needed

  • 400G DR4 uplinks over single-mode MPO-12 APC trunks; 100G SR4 and 25G server links over OM4
  • Low-loss MPO connectors, ≤ 0.35 dB per mated pair
  • Polarity method B throughout, matched to the cassettes
  • Labels by row, rack and port in the operator’s own scheme
  • Transceivers coded for the operator’s switches and tested in them

What we supplied

Equipment, by stage

  • Connect

    Backbone

    • ≈ 640 MPO-12 trunks, OS2 and OM4, cut to length from the rack elevations
    • 1U and 4U panels with MPO-LC cassettes
    • Polarity method B end to end
    MPO cabling on ZeroLine Connect
  • Connect

    Patching

    • ≈ 6,800 LC duplex and MPO patch cords
    • Colour-coded by service and labelled at both ends
  • Connect

    Optics

    • ≈ 1,400 transceivers: 400G DR4, 100G SR4 and 25G SR
    • Coded for the operator’s switch platform
    • 2 % spares kept on site
    Transceivers on ZeroLine Connect

Acceptance

How it was proven

  1. Insertion loss measured for every assembly, with the result on a QR label
  2. End-face images for every MPO connector
  3. Every transceiver tested in the target switch model before packing
  4. Installer’s site test of every trunk with an optical loss test set

Results

What it achieved

Racks
200
Delivered
2 lots, 5 and 6 weeks after order
Trunks passing the site test
100 %
Transceivers dead on arrival
3 of ≈ 1,400 (0.2 %), replaced from spares the same day
Hall ready
On the planned date

Schedule

From contract to running

  1. 01

    Design check

    Polarity, trunk lengths and labels checked against the rack elevations and the installer’s drawings.

    Week 1

  2. 02

    Make and test

    Trunks, cassettes and cords made to length and tested; transceivers coded and tested in the switch.

    Weeks 2–5

  3. 03

    Ship by row

    Packed by row and rack: lot 1 by air, lot 2 by sea.

    Weeks 5–6

  4. 04

    Install and test

    The installer pulls and tests rack by rack; spares cover the three failed transceivers.

    Weeks 7–9

Who did what

One contract, several factories

ZeroLine

  • Found a polarity mismatch between the installer’s drawings and the cassette type before anything was made
  • Worked out every trunk length from the rack elevations, with slack to the operator’s rule
  • One contract for cabling from two factories and optics from one module maker
  • Packed and labelled by row, so the installer could work rack by rack

The factories

  • Two Optics Valley factories made the trunks, cassettes and cords
  • A module maker in Wuhan coded and tested the transceivers
How the work is split on every project

Settle polarity on paper. Changing cassettes after the trunks are made costs weeks; changing a drawing costs an hour.

What we tell the next buyer

Start a project

Start a project like this

An empty plant, a part, a network or a product idea. Tell us where you are starting. An engineer replies with a plan and a quote.

What do you need?
Message us on WhatsApp