Key takeaways
- Write the SAT protocol into the contract together with the FAT protocol: the checks, the numeric limits, the length of the run, whose materials and operators are used, and which stops and defects count against the supplier.
- A SAT is not commissioning. Commissioning is the supplier getting the line to run; the SAT is the buyer confirming, against limits fixed in advance, that it runs at your site with your materials and your people.
- Prove safety again on site. The line was split, shipped and reconnected, so every emergency stop, guard, interlock and protective-earth connection is challenged or measured again, not taken over from the FAT record.
- Run the performance test long and with your own crews, for example 72 hours across three shifts. Stops and defects caused by the site come out of the figures only when they are logged with evidence and agreed at a daily review.
- Test the links to MES, plant utilities, the fire alarm and the BMS signal by signal against an agreed interface list. A line that runs at rate but loses records when the network drops has not passed.
- Sort open items into categories A, B and C. No A item may be open at signing; the signed final acceptance certificate releases the final-acceptance payment and starts the warranty.
What is a site acceptance test?
A site acceptance test (SAT) is the documented test that a machine or production line passes at the buyer’s own site after it has been installed and commissioned. It repeats the checks that transport and reassembly can undo, such as safety functions, electrical protection and calibration, and it adds what the supplier’s factory could not test: your power and compressed air, your raw materials, your operators and the systems the equipment connects to. The SAT ends with a signed record that accepts the equipment, accepts it with listed open items, or lists what must be fixed and retested. In many contracts that signature is final acceptance: it releases a payment and starts the warranty.
In software, the nearest term is user acceptance testing (UAT), which checks an application against business requirements; this guide is about equipment.
Download the template
Download the SAT checklist (Excel). It has the 30 checks below with evidence and result columns, the acceptance limits, a blank site performance-run sheet that calculates output, first-pass yield and availability as you type and checks them against your limits, the run from the illustrative example on this page, a daily log for classifying each stop and failed unit, a punch list with A, B and C categories, and a final acceptance certificate. Use and adapt it freely. Its companion for the test at the supplier’s factory is the factory acceptance test (FAT) checklist.
SAT, FAT, commissioning and SIT compared
| FAT | Commissioning | SAT | SIT | |
|---|---|---|---|---|
| Where | The supplier’s factory | Your site | Your site | Your site |
| When | Before the equipment is crated | After installation | After commissioning, once the supplier declares the line ready | With or after the SAT, when the connected systems are ready |
| Who runs it | The supplier; you witness | The supplier’s engineers | Your operators run the line to the protocol, the supplier’s engineers advise, both sign | You or your integrator, with every supplier involved |
| What it proves | The equipment meets the specification before it leaves | It starts, runs and makes good parts; settings are tuned | It meets the contract limits at your site, with your materials, people and utilities | It works with MES, plant utilities, the fire alarm, the BMS and other machines |
| Who pays | Usually in the equipment price; you pay your witnesses’ travel | The supplier’s engineers as priced in the contract; you provide utilities, materials, lifting and local labour | As commissioning; retests caused by the supplier at its cost | Shared according to each contract’s interface responsibilities |
| Usually tied to | The payment that releases shipment | No payment by itself | The final-acceptance payment and the warranty start | Part of the SAT or of plant handover |
IEC 62381:2024 sets requirements and checklists for the FAT, SAT and SIT of process-industry automation systems; this edition also adds an optional factory integration test (FIT). IEC 62337 describes commissioning of electrical, instrumentation and control systems as the phase between completion of erection and the owner’s acceptance of the plant. Neither sets output or yield numbers. Those come from your contract.
Machine contracts use other names for the same gate: final acceptance test, performance test, or provisional acceptance at the SAT with final acceptance at the end of the warranty. A plant built under a FIDIC Plant and Design-Build (Yellow Book) contract has Tests on Completion before taking-over, followed by a Defects Notification Period. Whatever the names, write down which signature releases which payment and starts the warranty.
How to run a SAT, step by step
- Agree the protocol with the contract. The SAT protocol is an annex signed with the purchase contract, like the FAT protocol: the checks, the numeric limits, the length of the performance run, the materials you supply and in what quantity, the operators, and who provides utilities, lifting and local labour. The signed FAT record adds the tests left for site and any minor items still open.
- Check site readiness before shipment. Foundations, floor load, power, compressed air, water, extraction, network and access routes are checked against the supplier’s site requirements, so the line does not wait in crates.
- Install and walk down. Inspect for transport damage on arrival, set and level the equipment, reconnect every split point and remove transport locks. A joint walkdown against the as-built drawings closes installation.
- Commission. The supplier’s engineers check signals and drives, bring up utilities, dry-run, make first parts with your materials and tune the settings. This is the supplier’s work, not the test.
- Declare readiness and freeze. The supplier gives written notice that the line is ready. Both sides confirm the preconditions (materials in stock, crews trained for the run, utilities stable) and freeze the recipe and software versions.
- Test safety and functions. Challenge every safety function on site and verify the electrical protection after reassembly; then modes, alarms, changeovers and reject paths.
- Run the performance test. Your operators run the line for the agreed window with your materials. Output, stops and defects are logged per shift and classified at a daily review signed by both sides.
- Test integration. MES data exchange, upstream and downstream handshakes, plant utilities, fire alarm and BMS signals are tested against the interface list, including what happens when a link fails.
- Check training and handover. Operators and maintenance staff show they can run and maintain the line; as-built documents, software, backups, passwords and spares are handed over.
- Sort the punch list and sign. Every open item gets a category, an owner and a date. With no category A item open, both sides sign the final acceptance certificate, which states the warranty start and the payment it releases.
The checklist: 30 checks in six groups
Each check has a pass criterion; the template adds the evidence to attach. Enter N/A only with a written reason and the buyer’s approval. The process checks are written for a battery module and PACK line. For a single machine such as a laser cutter or welder, keep the installation, safety and handover groups and make check 13 a test on your own parts at the settings you were quoted: cut quality, accuracy and speed on your sheet, or strength on your joints. For a fiber cable line, measure line speed and the properties your cable specification names, usually from the IEC 60794 family, on finished reels.
Preconditions and installation
| Check | Passes when |
|---|---|
| 01 SAT protocol | The protocol and its limits are signed, test materials are in stock, and the items deferred from the FAT are listed |
| 02 Arrival inspection | Crates, shock and tilt indicators and the equipment were inspected on arrival; transport damage is recorded and repaired or replaced |
| 03 Position and levelling | Positions match the approved layout; level, alignment and anchoring are within the supplier’s installation tolerances |
| 04 Split points | Every mechanical, pneumatic, electrical and data connection separated for shipment is reconnected and checked; transport locks are removed |
| 05 Configuration | Hardware, software versions and recipes match the FAT record, or every change is listed and approved |
Utilities and safety
| Check | Passes when |
|---|---|
| 06 Power and earthing | Voltage, frequency, phase rotation and the earthing system match the rating plate; protective bonding is continuous across reconnected sections |
| 07 Air, water, cooling and extraction | Pressure, flow, air quality, coolant temperature and extraction flow meet the specification with the whole line running, not at idle |
| 08 Electrical verification | The verifications described in clause 18 of IEC 60204-1, such as protective bonding continuity, insulation resistance and functional tests, are repeated where the line was reconnected, and the results recorded |
| 09 Emergency stops and guards | Every emergency stop, interlocked guard and light curtain is challenged on site; reset alone never restarts motion |
| 10 Laser and process hazards | Laser enclosures, viewing windows and interlocks are intact after transport; high-voltage test areas, fume and dust are controlled as in the safety design |
| 11 Risk assessment and permits | The risk assessment is updated for the installed layout, and any inspection that local law or your insurer requires has been done by the party the contract names |
Functional and performance run at site
| Check | Passes when |
|---|---|
| 12 Modes and alarms | Manual, setup and automatic modes, homing, alarms and recipe selection behave as at the FAT |
| 13 Quality on your materials | First articles made from your own materials pass your quality department’s inspection against the product drawing and specification |
| 14 Test equipment after transport | Torque, leak, electrical and dimensional test equipment is calibrated or verified on site, and the master parts are classified correctly |
| 15 Performance run | Your operators run the agreed window with frozen settings; output, first-pass yield and availability meet the contract limits |
| 16 Changeover and variants | Every product variant in the contract is run; changeover time and recipe interlocks meet the agreed target |
| 17 Traceability and rejects | Every unit of the run has complete records; a defective unit cannot leave the line as good |
| 18 Utility loss and recovery | After a controlled loss of site power, air and network, the line reaches a safe state, recovers by the approved sequence and keeps its records |
Integration with site systems
| Check | Passes when |
|---|---|
| 19 MES and ERP | Work orders, unit identities and results pass both ways in the agreed format; records buffered during a network loss arrive afterwards without gaps or duplicates |
| 20 Connected equipment | Handshakes with conveyors, AGVs, warehouses and other suppliers’ machines work at full rate, including blocked and starved conditions |
| 21 Plant utilities and rooms | Signals and interlocks with central compressors, chillers, extraction and dry-room or clean-room conditions work, with alarms where agreed |
| 22 Fire alarm and BMS | Each fire-alarm and gas-detection input produces the response in the agreed cause-and-effect matrix, and the agreed line alarms reach the BMS or SCADA |
Training and handover
| Check | Passes when |
|---|---|
| 23 Operator training | Each crew can run the line, change over and clear the common faults; attendance and a practical check are recorded |
| 24 Maintenance training | Maintenance staff carry out the preventive tasks, calibration checks and fault-finding in the manual under supervision |
| 25 As-built documents | Manuals, electrical and pneumatic drawings and the parameter list include every change made on site, in the agreed language |
| 26 Software and access | Final PLC, HMI and robot programs are backed up and a restore is shown; passwords and licences are handed over; remote access follows the route you approved |
| 27 Spares and tools | Commissioning spares, the recommended spare-parts kit and special tools are counted against the list |
Punch list and sign-off
| Check | Passes when |
|---|---|
| 28 Punch list | Every open item has a category, an owner and a due date; no category A item is open |
| 29 Limits and retests | Every numeric limit is met, and every retest is recorded with what was changed and who approved it |
| 30 Final acceptance certificate | Both parties sign; the certificate lists the open B and C items and states the acceptance date, the warranty start and the payment it releases |
The numbers to agree in the contract
A SAT without numbers turns the final payment into an argument. Agree these limits in the technical agreement, together with the FAT limits. The example values are for the same illustrative storage PACK line as the FAT worked example: 48-cell packs, designed for 8 cells per minute, so one pack every 6 minutes.
| Criterion | Example limit | How it is measured |
|---|---|---|
| Test window | 72 hours: 9 shifts of 480 minutes, run by your three crews | Continuous; the supplier’s engineers advise but do not operate |
| Sustained output | At least 7.60 cell equivalents per minute (95% of the design rate) | Unique completed packs at the line exit, divided by available time: the window minus agreed site-caused stops |
| Availability | At least 97.0% | Run time divided by available time; equipment stops count against it |
| First-pass yield | At least 99.0% | First-pass good divided by completed packs less those failed for agreed non-equipment causes; the all-cause figure is reported too |
| Safety | Every challenge passes; no unexpected restart | Challenge log |
| Traceability and data | Complete records for every unit; no lost or duplicate records after a network loss | MES reconciliation |
| Integration | Every action in the fire-alarm cause-and-effect matrix and every signal the line needs to run passes | Signed interface test sheets |
| Training | All crews and the named maintenance staff signed off | Training records |
| Closure | No open category A item | Punch list |
Decide in advance what counts as site-caused. Most SAT disputes are about blame, not arithmetic. List what does not count against the line: a plant utility outside its agreed specification, a shortage of materials, materials outside their incoming specification, operator actions against the trained procedure, and other suppliers’ equipment. Everything else counts. Log each event when it happens with its evidence, such as the utility log or the incoming inspection record, and have both sides sign the classification at a daily review. An exclusion argued after the run is a negotiation, not a measurement. If site-caused stops exceed an agreed share of the window, for example 10%, extend or repeat the run rather than calculate on a short base.
Example SAT report (illustrative)
This is an illustrative example. The line, the days and every figure are made up to show what a complete SAT record and its calculations look like; it is not a customer’s record. It continues the illustrative storage PACK line from the FAT guide.
| Field | Entry |
|---|---|
| Equipment | Storage PACK line, 48-cell LFP packs (1P48S), design 8 cells per minute |
| Protocol | SAT protocol annexed to the contract, with the limits above |
| Test window | Days 2 to 4: 72 hours, 9 shifts of 480 minutes, the buyer’s crews A, B and C |
| Materials | The buyer’s cells, enclosures and busbars from its approved suppliers |
| Frozen configuration | Recipe and software versions accepted at the FAT, plus two approved site changes |
| Witnesses | The buyer’s production, quality and maintenance leads; the supplier’s commissioning lead |
| Measure | Limit | Result | Verdict |
|---|---|---|---|
| Safety challenges, day 1 | All pass, no unexpected restart | 24 of 24 passed | Pass |
| Site-caused stops | Logged and agreed daily | 60 minutes: plant compressor trip 40, cell shortage 20 | Excluded |
| Equipment stops | Count against the line | 95 minutes | Counted |
| Completed packs | 681 in 4,260 available minutes | ||
| Output | At least 7.60 cell equivalents per minute | 7.67 (95.92% of design) | Pass |
| Availability | At least 97.0% | 97.77% | Pass |
| First-pass yield, all causes | Reported | 98.83% (673 of 681) | For information |
| First-pass yield for acceptance | At least 99.0% | 99.26% (673 of 678) | Pass |
| Network-loss test, day 5 | No lost or duplicate records | 3 records lost; day 7 retest: none lost in 5 outages | Fail, then pass |
| Fire alarm and BMS, day 5 | Every matrix action passes | 12 of 12 actions; one chiller alarm, for monitoring only, not mapped to the BMS | Pass, item P03 open |
| Training, day 6 | All crews and 4 maintenance technicians signed off | Signed off | Pass |
| Decision, day 8 | No open category A item | Final acceptance signed with 2 B and 3 C items open | Accepted |
The exclusion rule decided the yield. Eight packs failed first pass. Five had equipment causes: three weld alarms, one torque result out of limit and one end-of-line test fault from a loose sensing connector. Three had causes both sides agreed at the daily reviews were not the line’s: two packs failed the leak test with enclosure gaskets outside their incoming specification, confirmed by the incoming inspection record, and one pack label was scanned to the wrong work order against the trained procedure. Counted against all causes, first-pass yield was 98.83% and would have failed. Without the exclusion rule in the contract, final acceptance would have turned on an argument about three packs.
The A item and its retest. On day 5, a 10-minute network outage left three pack records in the line’s local buffer that never reached the MES; they were recovered from the line’s database. Complete traceability is an acceptance limit, so this was a category A item. The supplier enlarged the buffer and made the line resend each record until the MES acknowledges it. The fix changed data handling but not line flow or counting, so the retest covered the integration test and a regression check: five outages of 10 to 30 minutes with no lost or duplicate records, and a reconciliation of 200 packs made after the change. The performance run was not repeated.
The punch list at signing:
| Item | Category | Finding | Owner | Due | Status |
|---|---|---|---|---|---|
| P01 | A | Three pack records lost after a network outage | Supplier, controls | Day 7 | Closed: 5 outages, none lost |
| P02 | B | As-built electrical drawings missing the two site changes | Supplier, documentation | Day 30 | Open |
| P03 | B | Chiller fault alarm not mapped to the plant BMS; the line protects itself locally | Supplier and the buyer’s BMS contractor | Day 21 | Open |
| P04 | C | Transport scratch on a conveyor guard | Supplier | Day 30 | Open |
| P05 | C | Two cabinet labels missing in the site language | Supplier | Day 30 | Open |
| P06 | C | One gripper pad short in the spare-parts kit | Supplier | Day 45 | Open |
Final acceptance was signed on day 8. The certificate gives that date as the start of the warranty, releases the final-acceptance payment less an agreed amount held back until the two B items close, and lists P02 to P06 with owners and dates. The figures describe this 72-hour window; they are not a long-term output or yield guarantee.
How the run figures are calculated
The example above, with an ideal cycle of 6 minutes per 48-cell pack:
| Figure | Formula | Example |
|---|---|---|
| Available time | Window − agreed site-caused stops | 4,320 − 60 = 4,260 minutes |
| Run time | Available time − equipment stops | 4,260 − 95 = 4,165 minutes |
| Output | Completed packs × 48 ÷ available time | 681 × 48 ÷ 4,260 = 7.67 cell equivalents per minute |
| Output against design | Completed packs × ideal cycle ÷ available time | 681 × 6 ÷ 4,260 = 95.92% |
| Availability | Run time ÷ available time | 4,165 ÷ 4,260 = 97.77% |
| First-pass yield, all causes | First-pass good ÷ completed | 673 ÷ 681 = 98.83% |
| First-pass yield for acceptance | First-pass good ÷ (completed − agreed exclusions) | 673 ÷ 678 = 99.26% |
Availability follows the usual OEE definition, run time over planned production time, with the agreed site-caused stops taken out of the planned time. The template’s site run sheet does these sums per shift and for the whole window.
When the SAT fails
A failed SAT is a list of work, not the end of the contract, provided the contract says what happens next. Put every failure on the punch list with a category:
| Category | What it means | Effect on acceptance | Examples |
|---|---|---|---|
| A | A safety failure, a missed contract limit, lost data or anything that stops production | Blocks acceptance until fixed and retested | Unexpected restart, yield below the limit, lost records |
| B | The line meets the limits, but something contracted is missing or incomplete | Acceptance can be signed with the item listed, an owner, a deadline and money held back | Incomplete as-built drawings, an alarm not mapped to the BMS |
| C | Cosmetic or minor items | Listed and closed within an agreed time, often during the warranty | Paint damage, missing labels |
Industries define punch-list categories differently; what counts is that your contract defines them.
- Retest what the fix touched. A safety or control fix repeats the affected challenges and a regression check. A fix that changes line flow, cycle time or how units are counted repeats the full performance run. Record what changed, the retest result and who approved it.
- Limit the rounds. Agree how many retests the supplier gets, for example two, and how long each may take. After that the contract’s remedies apply: a price reduction or liquidated damages for an output or yield shortfall, further work at the supplier’s cost, and as a last resort rejection and refund. Write them down before the build; after a failed SAT, the unpaid balance is most of the leverage you have left.
- Watch for deemed acceptance. Many supplier contracts treat the line as accepted if the SAT has not happened within a set number of days after delivery or installation, or once the buyer uses it for commercial production. That is fair when the delay is yours. Make the clock start only from the supplier’s written readiness notice, exclude delays the supplier causes, and never let it override an open safety item.
Final acceptance, payment and warranty
- Tie the final payment to the signed certificate. In the split common for lines bought in China, 30% advance, 30% on shipment after factory acceptance, 30% after final acceptance and 10% after the warranty period, the SAT signature releases the third payment. Our payment terms page covers letters of credit and other ways to protect it.
- Hold back money for B items, not the whole payment. An agreed amount per item, released when it closes, keeps the supplier engaged without blocking payment for a line that already meets the limits.
- Start the warranty at final acceptance. A common formula is 12 months from final acceptance or 18 months from shipment, whichever ends first. The long-stop protects the supplier when the buyer delays the SAT; make sure a delay the supplier causes pushes it back.
- Keep the gates separate. Technical acceptance says the line met the protocol. Releasing money and starting the warranty follow from it, but they are commercial decisions you sign separately, as at the FAT.
How we install, commission and run the SAT
Our engineers install and commission the lines and plants we supply on your site; single machines can be installed with video guidance. We send a site readiness checklist with the order and check it with you before anything ships, commission the line to the agreed output and quality, and then run the SAT with your materials and your operators against the protocol in your contract. Training for operators and maintenance staff is part of the handover, and the punch list is closed as the contract sets out. Field engineers work in English. Send us your line scope and we draft the FAT and SAT protocols and their limits with the quotation. More on our installation, commissioning and training service; for the test before shipment, see the FAT checklist.