Buying guide MakePowerConnect

Site acceptance test (SAT) checklist for machines and production lines bought from China, with a free Excel template

A site acceptance test (SAT) is the test at the buyer's plant, after installation and commissioning, in which a machine or production line proves against limits agreed in the contract that it runs safely and at rate with the site's utilities, materials, operators and connected systems. Re-test safety after reassembly, run a long performance test with your own crews, test every interface, check training and documents, and sign final acceptance only with no blocking item open.

Key takeaways

  • Write the SAT protocol into the contract together with the FAT protocol: the checks, the numeric limits, the length of the run, whose materials and operators are used, and which stops and defects count against the supplier.
  • A SAT is not commissioning. Commissioning is the supplier getting the line to run; the SAT is the buyer confirming, against limits fixed in advance, that it runs at your site with your materials and your people.
  • Prove safety again on site. The line was split, shipped and reconnected, so every emergency stop, guard, interlock and protective-earth connection is challenged or measured again, not taken over from the FAT record.
  • Run the performance test long and with your own crews, for example 72 hours across three shifts. Stops and defects caused by the site come out of the figures only when they are logged with evidence and agreed at a daily review.
  • Test the links to MES, plant utilities, the fire alarm and the BMS signal by signal against an agreed interface list. A line that runs at rate but loses records when the network drops has not passed.
  • Sort open items into categories A, B and C. No A item may be open at signing; the signed final acceptance certificate releases the final-acceptance payment and starts the warranty.

What is a site acceptance test?

A site acceptance test (SAT) is the documented test that a machine or production line passes at the buyer’s own site after it has been installed and commissioned. It repeats the checks that transport and reassembly can undo, such as safety functions, electrical protection and calibration, and it adds what the supplier’s factory could not test: your power and compressed air, your raw materials, your operators and the systems the equipment connects to. The SAT ends with a signed record that accepts the equipment, accepts it with listed open items, or lists what must be fixed and retested. In many contracts that signature is final acceptance: it releases a payment and starts the warranty.

In software, the nearest term is user acceptance testing (UAT), which checks an application against business requirements; this guide is about equipment.

Download the template

Download the SAT checklist (Excel). It has the 30 checks below with evidence and result columns, the acceptance limits, a blank site performance-run sheet that calculates output, first-pass yield and availability as you type and checks them against your limits, the run from the illustrative example on this page, a daily log for classifying each stop and failed unit, a punch list with A, B and C categories, and a final acceptance certificate. Use and adapt it freely. Its companion for the test at the supplier’s factory is the factory acceptance test (FAT) checklist.

SAT, FAT, commissioning and SIT compared

FAT Commissioning SAT SIT
Where The supplier’s factory Your site Your site Your site
When Before the equipment is crated After installation After commissioning, once the supplier declares the line ready With or after the SAT, when the connected systems are ready
Who runs it The supplier; you witness The supplier’s engineers Your operators run the line to the protocol, the supplier’s engineers advise, both sign You or your integrator, with every supplier involved
What it proves The equipment meets the specification before it leaves It starts, runs and makes good parts; settings are tuned It meets the contract limits at your site, with your materials, people and utilities It works with MES, plant utilities, the fire alarm, the BMS and other machines
Who pays Usually in the equipment price; you pay your witnesses’ travel The supplier’s engineers as priced in the contract; you provide utilities, materials, lifting and local labour As commissioning; retests caused by the supplier at its cost Shared according to each contract’s interface responsibilities
Usually tied to The payment that releases shipment No payment by itself The final-acceptance payment and the warranty start Part of the SAT or of plant handover

IEC 62381:2024 sets requirements and checklists for the FAT, SAT and SIT of process-industry automation systems; this edition also adds an optional factory integration test (FIT). IEC 62337 describes commissioning of electrical, instrumentation and control systems as the phase between completion of erection and the owner’s acceptance of the plant. Neither sets output or yield numbers. Those come from your contract.

Machine contracts use other names for the same gate: final acceptance test, performance test, or provisional acceptance at the SAT with final acceptance at the end of the warranty. A plant built under a FIDIC Plant and Design-Build (Yellow Book) contract has Tests on Completion before taking-over, followed by a Defects Notification Period. Whatever the names, write down which signature releases which payment and starts the warranty.

How to run a SAT, step by step

  1. Agree the protocol with the contract. The SAT protocol is an annex signed with the purchase contract, like the FAT protocol: the checks, the numeric limits, the length of the performance run, the materials you supply and in what quantity, the operators, and who provides utilities, lifting and local labour. The signed FAT record adds the tests left for site and any minor items still open.
  2. Check site readiness before shipment. Foundations, floor load, power, compressed air, water, extraction, network and access routes are checked against the supplier’s site requirements, so the line does not wait in crates.
  3. Install and walk down. Inspect for transport damage on arrival, set and level the equipment, reconnect every split point and remove transport locks. A joint walkdown against the as-built drawings closes installation.
  4. Commission. The supplier’s engineers check signals and drives, bring up utilities, dry-run, make first parts with your materials and tune the settings. This is the supplier’s work, not the test.
  5. Declare readiness and freeze. The supplier gives written notice that the line is ready. Both sides confirm the preconditions (materials in stock, crews trained for the run, utilities stable) and freeze the recipe and software versions.
  6. Test safety and functions. Challenge every safety function on site and verify the electrical protection after reassembly; then modes, alarms, changeovers and reject paths.
  7. Run the performance test. Your operators run the line for the agreed window with your materials. Output, stops and defects are logged per shift and classified at a daily review signed by both sides.
  8. Test integration. MES data exchange, upstream and downstream handshakes, plant utilities, fire alarm and BMS signals are tested against the interface list, including what happens when a link fails.
  9. Check training and handover. Operators and maintenance staff show they can run and maintain the line; as-built documents, software, backups, passwords and spares are handed over.
  10. Sort the punch list and sign. Every open item gets a category, an owner and a date. With no category A item open, both sides sign the final acceptance certificate, which states the warranty start and the payment it releases.

The checklist: 30 checks in six groups

Each check has a pass criterion; the template adds the evidence to attach. Enter N/A only with a written reason and the buyer’s approval. The process checks are written for a battery module and PACK line. For a single machine such as a laser cutter or welder, keep the installation, safety and handover groups and make check 13 a test on your own parts at the settings you were quoted: cut quality, accuracy and speed on your sheet, or strength on your joints. For a fiber cable line, measure line speed and the properties your cable specification names, usually from the IEC 60794 family, on finished reels.

Preconditions and installation

Check Passes when
01 SAT protocol The protocol and its limits are signed, test materials are in stock, and the items deferred from the FAT are listed
02 Arrival inspection Crates, shock and tilt indicators and the equipment were inspected on arrival; transport damage is recorded and repaired or replaced
03 Position and levelling Positions match the approved layout; level, alignment and anchoring are within the supplier’s installation tolerances
04 Split points Every mechanical, pneumatic, electrical and data connection separated for shipment is reconnected and checked; transport locks are removed
05 Configuration Hardware, software versions and recipes match the FAT record, or every change is listed and approved

Utilities and safety

Check Passes when
06 Power and earthing Voltage, frequency, phase rotation and the earthing system match the rating plate; protective bonding is continuous across reconnected sections
07 Air, water, cooling and extraction Pressure, flow, air quality, coolant temperature and extraction flow meet the specification with the whole line running, not at idle
08 Electrical verification The verifications described in clause 18 of IEC 60204-1, such as protective bonding continuity, insulation resistance and functional tests, are repeated where the line was reconnected, and the results recorded
09 Emergency stops and guards Every emergency stop, interlocked guard and light curtain is challenged on site; reset alone never restarts motion
10 Laser and process hazards Laser enclosures, viewing windows and interlocks are intact after transport; high-voltage test areas, fume and dust are controlled as in the safety design
11 Risk assessment and permits The risk assessment is updated for the installed layout, and any inspection that local law or your insurer requires has been done by the party the contract names

Functional and performance run at site

Check Passes when
12 Modes and alarms Manual, setup and automatic modes, homing, alarms and recipe selection behave as at the FAT
13 Quality on your materials First articles made from your own materials pass your quality department’s inspection against the product drawing and specification
14 Test equipment after transport Torque, leak, electrical and dimensional test equipment is calibrated or verified on site, and the master parts are classified correctly
15 Performance run Your operators run the agreed window with frozen settings; output, first-pass yield and availability meet the contract limits
16 Changeover and variants Every product variant in the contract is run; changeover time and recipe interlocks meet the agreed target
17 Traceability and rejects Every unit of the run has complete records; a defective unit cannot leave the line as good
18 Utility loss and recovery After a controlled loss of site power, air and network, the line reaches a safe state, recovers by the approved sequence and keeps its records

Integration with site systems

Check Passes when
19 MES and ERP Work orders, unit identities and results pass both ways in the agreed format; records buffered during a network loss arrive afterwards without gaps or duplicates
20 Connected equipment Handshakes with conveyors, AGVs, warehouses and other suppliers’ machines work at full rate, including blocked and starved conditions
21 Plant utilities and rooms Signals and interlocks with central compressors, chillers, extraction and dry-room or clean-room conditions work, with alarms where agreed
22 Fire alarm and BMS Each fire-alarm and gas-detection input produces the response in the agreed cause-and-effect matrix, and the agreed line alarms reach the BMS or SCADA

Training and handover

Check Passes when
23 Operator training Each crew can run the line, change over and clear the common faults; attendance and a practical check are recorded
24 Maintenance training Maintenance staff carry out the preventive tasks, calibration checks and fault-finding in the manual under supervision
25 As-built documents Manuals, electrical and pneumatic drawings and the parameter list include every change made on site, in the agreed language
26 Software and access Final PLC, HMI and robot programs are backed up and a restore is shown; passwords and licences are handed over; remote access follows the route you approved
27 Spares and tools Commissioning spares, the recommended spare-parts kit and special tools are counted against the list

Punch list and sign-off

Check Passes when
28 Punch list Every open item has a category, an owner and a due date; no category A item is open
29 Limits and retests Every numeric limit is met, and every retest is recorded with what was changed and who approved it
30 Final acceptance certificate Both parties sign; the certificate lists the open B and C items and states the acceptance date, the warranty start and the payment it releases

The numbers to agree in the contract

A SAT without numbers turns the final payment into an argument. Agree these limits in the technical agreement, together with the FAT limits. The example values are for the same illustrative storage PACK line as the FAT worked example: 48-cell packs, designed for 8 cells per minute, so one pack every 6 minutes.

Criterion Example limit How it is measured
Test window 72 hours: 9 shifts of 480 minutes, run by your three crews Continuous; the supplier’s engineers advise but do not operate
Sustained output At least 7.60 cell equivalents per minute (95% of the design rate) Unique completed packs at the line exit, divided by available time: the window minus agreed site-caused stops
Availability At least 97.0% Run time divided by available time; equipment stops count against it
First-pass yield At least 99.0% First-pass good divided by completed packs less those failed for agreed non-equipment causes; the all-cause figure is reported too
Safety Every challenge passes; no unexpected restart Challenge log
Traceability and data Complete records for every unit; no lost or duplicate records after a network loss MES reconciliation
Integration Every action in the fire-alarm cause-and-effect matrix and every signal the line needs to run passes Signed interface test sheets
Training All crews and the named maintenance staff signed off Training records
Closure No open category A item Punch list

Decide in advance what counts as site-caused. Most SAT disputes are about blame, not arithmetic. List what does not count against the line: a plant utility outside its agreed specification, a shortage of materials, materials outside their incoming specification, operator actions against the trained procedure, and other suppliers’ equipment. Everything else counts. Log each event when it happens with its evidence, such as the utility log or the incoming inspection record, and have both sides sign the classification at a daily review. An exclusion argued after the run is a negotiation, not a measurement. If site-caused stops exceed an agreed share of the window, for example 10%, extend or repeat the run rather than calculate on a short base.

Example SAT report (illustrative)

This is an illustrative example. The line, the days and every figure are made up to show what a complete SAT record and its calculations look like; it is not a customer’s record. It continues the illustrative storage PACK line from the FAT guide.

Field Entry
Equipment Storage PACK line, 48-cell LFP packs (1P48S), design 8 cells per minute
Protocol SAT protocol annexed to the contract, with the limits above
Test window Days 2 to 4: 72 hours, 9 shifts of 480 minutes, the buyer’s crews A, B and C
Materials The buyer’s cells, enclosures and busbars from its approved suppliers
Frozen configuration Recipe and software versions accepted at the FAT, plus two approved site changes
Witnesses The buyer’s production, quality and maintenance leads; the supplier’s commissioning lead
Measure Limit Result Verdict
Safety challenges, day 1 All pass, no unexpected restart 24 of 24 passed Pass
Site-caused stops Logged and agreed daily 60 minutes: plant compressor trip 40, cell shortage 20 Excluded
Equipment stops Count against the line 95 minutes Counted
Completed packs 681 in 4,260 available minutes
Output At least 7.60 cell equivalents per minute 7.67 (95.92% of design) Pass
Availability At least 97.0% 97.77% Pass
First-pass yield, all causes Reported 98.83% (673 of 681) For information
First-pass yield for acceptance At least 99.0% 99.26% (673 of 678) Pass
Network-loss test, day 5 No lost or duplicate records 3 records lost; day 7 retest: none lost in 5 outages Fail, then pass
Fire alarm and BMS, day 5 Every matrix action passes 12 of 12 actions; one chiller alarm, for monitoring only, not mapped to the BMS Pass, item P03 open
Training, day 6 All crews and 4 maintenance technicians signed off Signed off Pass
Decision, day 8 No open category A item Final acceptance signed with 2 B and 3 C items open Accepted

The exclusion rule decided the yield. Eight packs failed first pass. Five had equipment causes: three weld alarms, one torque result out of limit and one end-of-line test fault from a loose sensing connector. Three had causes both sides agreed at the daily reviews were not the line’s: two packs failed the leak test with enclosure gaskets outside their incoming specification, confirmed by the incoming inspection record, and one pack label was scanned to the wrong work order against the trained procedure. Counted against all causes, first-pass yield was 98.83% and would have failed. Without the exclusion rule in the contract, final acceptance would have turned on an argument about three packs.

The A item and its retest. On day 5, a 10-minute network outage left three pack records in the line’s local buffer that never reached the MES; they were recovered from the line’s database. Complete traceability is an acceptance limit, so this was a category A item. The supplier enlarged the buffer and made the line resend each record until the MES acknowledges it. The fix changed data handling but not line flow or counting, so the retest covered the integration test and a regression check: five outages of 10 to 30 minutes with no lost or duplicate records, and a reconciliation of 200 packs made after the change. The performance run was not repeated.

The punch list at signing:

Item Category Finding Owner Due Status
P01 A Three pack records lost after a network outage Supplier, controls Day 7 Closed: 5 outages, none lost
P02 B As-built electrical drawings missing the two site changes Supplier, documentation Day 30 Open
P03 B Chiller fault alarm not mapped to the plant BMS; the line protects itself locally Supplier and the buyer’s BMS contractor Day 21 Open
P04 C Transport scratch on a conveyor guard Supplier Day 30 Open
P05 C Two cabinet labels missing in the site language Supplier Day 30 Open
P06 C One gripper pad short in the spare-parts kit Supplier Day 45 Open

Final acceptance was signed on day 8. The certificate gives that date as the start of the warranty, releases the final-acceptance payment less an agreed amount held back until the two B items close, and lists P02 to P06 with owners and dates. The figures describe this 72-hour window; they are not a long-term output or yield guarantee.

How the run figures are calculated

The example above, with an ideal cycle of 6 minutes per 48-cell pack:

Figure Formula Example
Available time Window − agreed site-caused stops 4,320 − 60 = 4,260 minutes
Run time Available time − equipment stops 4,260 − 95 = 4,165 minutes
Output Completed packs × 48 ÷ available time 681 × 48 ÷ 4,260 = 7.67 cell equivalents per minute
Output against design Completed packs × ideal cycle ÷ available time 681 × 6 ÷ 4,260 = 95.92%
Availability Run time ÷ available time 4,165 ÷ 4,260 = 97.77%
First-pass yield, all causes First-pass good ÷ completed 673 ÷ 681 = 98.83%
First-pass yield for acceptance First-pass good ÷ (completed − agreed exclusions) 673 ÷ 678 = 99.26%

Availability follows the usual OEE definition, run time over planned production time, with the agreed site-caused stops taken out of the planned time. The template’s site run sheet does these sums per shift and for the whole window.

When the SAT fails

A failed SAT is a list of work, not the end of the contract, provided the contract says what happens next. Put every failure on the punch list with a category:

Category What it means Effect on acceptance Examples
A A safety failure, a missed contract limit, lost data or anything that stops production Blocks acceptance until fixed and retested Unexpected restart, yield below the limit, lost records
B The line meets the limits, but something contracted is missing or incomplete Acceptance can be signed with the item listed, an owner, a deadline and money held back Incomplete as-built drawings, an alarm not mapped to the BMS
C Cosmetic or minor items Listed and closed within an agreed time, often during the warranty Paint damage, missing labels

Industries define punch-list categories differently; what counts is that your contract defines them.

  • Retest what the fix touched. A safety or control fix repeats the affected challenges and a regression check. A fix that changes line flow, cycle time or how units are counted repeats the full performance run. Record what changed, the retest result and who approved it.
  • Limit the rounds. Agree how many retests the supplier gets, for example two, and how long each may take. After that the contract’s remedies apply: a price reduction or liquidated damages for an output or yield shortfall, further work at the supplier’s cost, and as a last resort rejection and refund. Write them down before the build; after a failed SAT, the unpaid balance is most of the leverage you have left.
  • Watch for deemed acceptance. Many supplier contracts treat the line as accepted if the SAT has not happened within a set number of days after delivery or installation, or once the buyer uses it for commercial production. That is fair when the delay is yours. Make the clock start only from the supplier’s written readiness notice, exclude delays the supplier causes, and never let it override an open safety item.

Final acceptance, payment and warranty

  • Tie the final payment to the signed certificate. In the split common for lines bought in China, 30% advance, 30% on shipment after factory acceptance, 30% after final acceptance and 10% after the warranty period, the SAT signature releases the third payment. Our payment terms page covers letters of credit and other ways to protect it.
  • Hold back money for B items, not the whole payment. An agreed amount per item, released when it closes, keeps the supplier engaged without blocking payment for a line that already meets the limits.
  • Start the warranty at final acceptance. A common formula is 12 months from final acceptance or 18 months from shipment, whichever ends first. The long-stop protects the supplier when the buyer delays the SAT; make sure a delay the supplier causes pushes it back.
  • Keep the gates separate. Technical acceptance says the line met the protocol. Releasing money and starting the warranty follow from it, but they are commercial decisions you sign separately, as at the FAT.

How we install, commission and run the SAT

Our engineers install and commission the lines and plants we supply on your site; single machines can be installed with video guidance. We send a site readiness checklist with the order and check it with you before anything ships, commission the line to the agreed output and quality, and then run the SAT with your materials and your operators against the protocol in your contract. Training for operators and maintenance staff is part of the handover, and the punch list is closed as the contract sets out. Field engineers work in English. Send us your line scope and we draft the FAT and SAT protocols and their limits with the quotation. More on our installation, commissioning and training service; for the test before shipment, see the FAT checklist.

Site acceptance is the last step in how to buy a production line from China safely.

What is a site acceptance test (SAT)?

A site acceptance test is the documented test a machine or production line passes at the buyer's own site after installation and commissioning. It repeats the checks that transport and reassembly can undo, such as safety functions, electrical protection and calibration, and adds what the supplier's factory could not test: your utilities, your materials, your operators and the systems the equipment connects to. It ends with a signed record that accepts the equipment, accepts it with listed open items, or lists what must be fixed and retested.

What does SAT stand for in engineering?

In engineering projects SAT stands for site acceptance test: the acceptance test of equipment or an automation system at the place where it will operate, after installation. Its counterpart before shipment is the factory acceptance test (FAT). IEC 62381:2024 sets requirements and checklists for both in process-industry automation systems.

How does SAT testing work?

The protocol and its numeric limits are agreed in the contract. After installation and commissioning, the supplier gives written notice that the line is ready and both sides freeze its settings. Safety functions are challenged on site, then your operators run a performance test with your materials, for example 72 hours across three shifts, while output, stops and defects are logged and classified daily. Interfaces with MES, utilities, the fire alarm and the BMS are tested, training and documents are checked, and open items go on a punch list. With no blocking item open, both sides sign the final acceptance certificate.

What is the difference between FAT and SAT?

The factory acceptance test (FAT) runs at the supplier's factory before shipment and shows the equipment meets the specification there, usually with the supplier's utilities and often with sample materials. The site acceptance test (SAT) runs at your plant after installation and commissioning, with your power, air, materials, operators and connected systems, and shows it works in place. A FAT pass usually releases the shipment payment; a SAT pass usually releases the final-acceptance payment and starts the warranty.

What is systems acceptance testing?

In software, system or user acceptance testing checks a finished application against its requirements before it goes live; that meaning is separate from equipment acceptance. In plant projects, the test of a machine or line on its own at site is the SAT, and the test of it working together with the plant's other systems, such as MES, utilities, fire alarm and building management, is called the site integration test (SIT) in IEC 62381.

What are the four types of acceptance testing?

For equipment and automation systems, IEC 62381:2024 covers four: the factory acceptance test (FAT), an optional factory integration test (FIT) added in that edition, the site acceptance test (SAT) and the site integration test (SIT). In software testing, the forms usually named are user, operational, contractual and regulatory acceptance testing, plus alpha and beta testing.

What should a site acceptance test report include?

The equipment and serial numbers, the protocol revision, the test dates and window, the materials and crews used, and the frozen software and recipe versions. Then the result of every check with its evidence, the measured figures against each contract limit with the calculation, the daily log of stops and defects with how each was classified, the retests, the punch list with categories, owners and dates, and the decision. The signature page states the acceptance date, the warranty start and the payment it releases. The free Excel template on this page has a sheet for each.

What happens if a production line fails the site acceptance test?

The failures go on the punch list. Category A items, such as a safety failure, a missed output or yield limit or lost data, block acceptance until they are fixed and retested; B items can be accepted with an owner, a deadline and money held back; C items are minor and closed within an agreed time. Retest what the fix touched, and repeat the full performance run when the fix changes line flow or counting. The contract should limit the number of retests and say which remedies apply after that.

Start a project

Ask for a SAT protocol for your line

An empty plant, a part, a network or a product idea. Tell us where you are starting. An engineer replies with a plan and a quote.

What do you need?
Message us on WhatsApp

Start a project